EPM26641 HELIOS FINAL REPORT FOR PERIOD ENDING 14 JANUARY 2022

URL: https://geoscience.data.qld.gov.au/dataset/cr130465

This is the final report for EPM26641 covering the period 16 October 2018 to 14 January 2022. No ground activity was completed during this period. 2D modelling was performed to guide field work however restrictions arising from the Covid 19 pandemic halted field work. Results did not reveal any deep conductors of interest. The permit was surrendered 14 January 2022 with the holder shifting focus to more prospective ground.

Data and Resources

This dataset was harvested

Additional Info

Field Value
Source https://geoscience.data.qld.gov.au/dataset/cr130465
Author GSQOpenData@dnrme.qld.gov.au
Maintainer GSQOpenData@dnrme.qld.gov.au
Version 1.0
Last Updated March 8, 2024, 17:03 (AEST)
Created May 8, 2023, 19:55 (AEST)
harvest_object_id 7bee5bb7-f469-4904-937e-c40babb1cf28
harvest_source_id ab92c79e-7b6d-4ae9-b70b-a0e84e78006b
harvest_source_title Geoscience Harvester